๐Review Complete๐ง Renovation/Alteration๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Ray Dr. and Ray Court-Paving, Drainage & Utility Reconstruction
Ray Dr. & Ray Court, Haltom City, TX, 76117
Construction50%
๐Project Metrics
TDLR #TABS2025018047$200K
Project Value
3,292
Square Feet
$61/sqft
Cost/SqFt
1 year
Duration
Registered:May 2, 2025
Start:Jan 24, 2025
Target:Jan 31, 2026
Remaining:52 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Construction of 3,292 lineal foot of sidewalk and ramp improvements
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
May 2, 2025
Review Complete
May 2, 2025
Construction Start
January 24, 2025
Expected Completion
January 31, 2026
๐Related Projects
Property Owner
๐ค
CIty of Haltom City
Contact: Autumn Permenter, P.E.
4200 Hollis St., Haltom City, Texas 76117