📝Review Complete🏗️ New Construction💵 This project is privately funded, on private land for private use.
Fairmont Strip Center
1247 S 13th St, La Porte, TX, 77571
Construction50%
📊Project Metrics
TDLR #TABS2025018203$500K
Project Value
8,673
Square Feet
$58/sqft
Cost/SqFt
2 years
Duration
Registered:May 5, 2025
Start:Jun 16, 2025
Target:Jun 14, 2027
Remaining:551 days
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
New Shopping Center
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
May 5, 2025
Review Complete
May 5, 2025
Construction Start
June 16, 2025
Expected Completion
June 14, 2027