๐Review Complete๐ง Renovation/Alteration๐ต This project is privately funded, on private land for private use.
HMWB Central Plant Emergency Power
18220 TX-249, Houston, TX, 77070
Construction50%
๐Project Metrics
TDLR #TABS2025018268$4.0M
Project Value
1,000
Square Feet
$4000/sqft
Cost/SqFt
9 months
Duration
Registered:May 6, 2025
Start:Jul 1, 2025
Target:Mar 31, 2026
Remaining:111 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Add new utility yard and renovate portion of existing utility plant for new emergency generator and associated equipment.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
May 6, 2025
Review Complete
May 6, 2025
Construction Start
July 1, 2025
Expected Completion
March 31, 2026
๐Related Projects
๐๏ธBy Design Firm
$21.6M totalMHHS League City CCC - CT Equipment Exchange
League Cityยท$500K
Houston Methodist Baytown Cath Lab Cath Lab 1
Baytownยท$500K
MHSL Hospital Expansion: Hospitalist Office Reno Package
Sugar Landยท$100K
Houston Methodist Baytown Emergency Care Center
Baytownยท$9.5M
Property Owner
๐ค
Houston Methodist Willowbrook Hospital
Contact: Rodney Villafranca
6560 Fannin Ste 201, Houston, Texas 77030
Design Firm
๐๏ธ
PhiloWilke Partnership
6 projects ยท $21.6M
10350 Richmond Avenue, Suite 400, Houston, Texas 77042