Aurora Ave to Fortuna St, San Antonio, TX, 78227
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025019101
$15.8M
Project Value
15,400
Square Feet
$1026/sqft
Cost/SqFt
2 years
Duration
Registered:May 15, 2025
Start:Sep 1, 2025
Target:Sep 1, 2027
Remaining:630 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Construct a 10 ft wide concrete trail along Zazamora Creek from Alderete Park to Tierra de Sol Park app 2.2 miles Includes trail connections to Monterrey Park, Arroyo Park and 41st

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 15, 2025
Review Complete
May 15, 2025
Construction Start
September 1, 2025
Expected Completion
September 1, 2027

๐Ÿ—บ๏ธProject Location

Loading map...

Quick Actions

TDLR ID: TABS2025019101

Property Owner

Design Firm

๐Ÿ›๏ธ
Ardurra Group Inc
3 projects ยท $17.9M
8918 Tesoro Dr Ste 401, San Antonio, Texas 78217

Registered Accessibility Specialist