๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Potter County District Court - Phase 2
501 S Fillmore St 501 S Fillmore St, Amarillo, TX, 79101
Construction50%
๐Project Metrics
TDLR #TABS2025019210$2.0M
Project Value
114,850
Square Feet
$18/sqft
Cost/SqFt
9 months
Duration
Registered:May 16, 2025
Start:May 20, 2025
Target:Feb 20, 2026
Remaining:72 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
After the District Court building is demolished, the site will be improved, and a new parking lot will get built in place. There will be an exit-only stair connecting to the County Courthouse thru an existing maintenance underground tunnel to remain
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
May 16, 2025
Review Complete
May 16, 2025
Construction Start
May 20, 2025
Expected Completion
February 20, 2026