📋Project Registered🏗️ New Construction💵 This project is privately funded, on private land for private use.
TRUCK STOP AND CONVENIENCE STORE
141 FM 2429,, Bellville, TX, 77418
Pre-Construction15%
📊Project Metrics
TDLR #TABS2025019543$1.5M
Project Value
6,000
Square Feet
$250/sqft
Cost/SqFt
7 months
Duration
Registered:May 21, 2025
Start:Sep 2, 2025
Target:Mar 30, 2026
Remaining:110 days
📋
Project Registered
Project has been registered with TDLR and is in pre-construction phase
📋Scope of Work
New Truck stop
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
May 21, 2025
Construction Start
September 2, 2025
Expected Completion
March 30, 2026