๐Ÿ“Review Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

McKinney ISD Evans Middle School Infant Daycare area

6998 Eldorado Pkwy, Mckinney, TX, 75070
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025019641
$277K
Project Value
5,200
Square Feet
$53/sqft
Cost/SqFt
2 months
Duration
Registered:May 22, 2025
Start:May 30, 2025
Target:Jul 31, 2025
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

To include modifications of 5 existing classrooms, totalling roughly 5,200 sq. ft. Will have 1 new exterior door, 3 new single use RR, offices, and classrooms to accommodate an infant daycare.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 22, 2025
Review Complete
May 22, 2025
Construction Start
May 30, 2025
Expected Completion
July 31, 2025

๐Ÿ“Location & Views

Open in MapsGet Directions|33.17438, -96.70802

Quick Actions

TDLR ID: TABS2025019641

Design Firm

Registered Accessibility Specialist

๐Ÿ“‹
BLAIR,BAKER
RAS #19
539 W COMMERCE ST SUITE 180, DALLAS, TX 75208