📝Review Complete🔧 Renovation/Alteration💵 This project is privately funded, on private land for private use.
RENOVATIONS & IMPROVEMENTS TO BOUTIQUE HOTEL EL PASO
6140 Gateway Bloulevard East, El Paso, TX, 79905
Construction50%
📊Project Metrics
TDLR #TABS2025019777$2.5M
Project Value
42,500
Square Feet
$59/sqft
Cost/SqFt
9 months
Duration
Registered:May 27, 2025
Start:May 31, 2025
Target:Feb 28, 2026
Remaining:80 days
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
Renovation of an existing hotel
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
May 27, 2025
Review Complete
May 27, 2025
Construction Start
May 31, 2025
Expected Completion
February 28, 2026