๐Review Complete๐ง Renovation/Alteration๐ต This project involves public funds, public land, or is a Federally funded roadway project.
SWM - NW Collection/Maintenance Concrete
1245 Judiway Street, Houston, TX, 77018
Construction50%
๐Project Metrics
TDLR #TABS2025019813$729K
Project Value
26,915
Square Feet
$27/sqft
Cost/SqFt
1y 11mo
Duration
Registered:May 27, 2025
Start:Oct 1, 2024
Target:Sep 1, 2026
Remaining:265 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Repair of existing concrete.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
May 27, 2025
Review Complete
May 27, 2025
Construction Start
October 1, 2024
Expected Completion
September 1, 2026
๐Related Projects
๐คBy Owner
$17.3M totalCentral Utility Plant Renovation and Upgrade EN03 Trailer Power Enabling Package
Houstonยท$300K
Hirsch Road Bridge Replacement Over HCFCD P118-12-00 (Ditch 19 DD#6)
Houstonยท$1.3M
IAH T-E Restrooms Gate 11
Houstonยท$3.2M
Navigation Boulevard From Lockwood to Mack Street
Houstonยท$9.0M
Property Owner
๐ค
City of Houston
Contact: Brian Fermin
6 projects ยท $17.3M
PO Box 1562, Houston, Texas 77251
Design Firm
๐๏ธ
Ryden Architecture, LLC
6 projects ยท $12.4M
909 Wakefield Dr, Houston, Texas 77018