CCISD Parking Lot Improvements Project 3-Port O'Connor Elementary

508 Monroe St, Port O Connor, TX, 77982
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025019991
$197K
Project Value
28,500
Square Feet
$7/sqft
Cost/SqFt
7 months
Duration
Registered:May 29, 2025
Start:May 30, 2025
Target:Dec 26, 2025
Remaining:16 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

The construction of approximately 27,000 sf of flexible pavement parking lot & 1,500 sf of concrete sidewalk.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 29, 2025
Review Complete
May 29, 2025
Construction Start
May 30, 2025
Expected Completion
December 26, 2025

๐Ÿ—บ๏ธProject Location

Loading map...

Quick Actions

TDLR ID: TABS2025019991

Design Firm

Registered Accessibility Specialist

๐Ÿ“‹
TIMOTHY D,WESTPHAL
RAS #161
2616 L BAKER ROAD, GOLIAD, TX 77963