Cherryhurst Sidewalk Improvements
bounded by Fairview, Wesheimer, Yupon, & Dunlavy, Houston, TX, 77006
Construction50%
๐Project Metrics
TDLR #TABS2025020177$1.0M
Project Value
290,000
Square Feet
$3/sqft
Cost/SqFt
10 months
Duration
Registered:May 30, 2025
Start:Sep 1, 2025
Target:Jul 10, 2026
Remaining:212 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Sidewalk and wheelchair ramp replacements. Driveway replacement. Tree protection
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
May 30, 2025
Review Complete
May 30, 2025
Construction Start
September 1, 2025
Expected Completion
July 10, 2026
๐Related Projects
Property Owner
๐ค
Montrose Redevelopment Authority
Contact: Matt Brollier
3200 Southwest Freeway, Suite 2600, Houston, Texas 77027
Design Firm
๐๏ธ
HR Green
4 projects ยท $20.1M
11750 Katy Freeway, Suite 400, Houston, Texas 77079