๐Project Closed๐ง Renovation/Alteration๐ต This project is privately funded, on private land for private use.
MCC Central Utilities: Boiler Enclosure
1400 College Dr., Waco, TX, 76708
Completed100%
๐Project Metrics
TDLR #TABS2025020739$1.0M
Project Value
984
Square Feet
$1016/sqft
Cost/SqFt
6 months
Duration
Registered:Jun 6, 2025
Start:Jul 1, 2025
Target:Dec 31, 2025
Remaining:21 days
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Create an enclosure of approximately 984 square feet to separate the boiler area from the rest of the central utility plant and provide 3 new boilers.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
June 6, 2025
Project Closed
June 6, 2025
Construction Start
July 1, 2025
Expected Completion
December 31, 2025
๐Related Projects
๐คBy Owner
$1.6M totalProperty Owner
๐ค
McLennan Community College
Contact: Ted Gonzalez
4 projects ยท $1.6M
1400 College Dr, Waco, Texas 76708