๐Ÿ“Review Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

W Boydstun Avenue/Forest Trace

S Lakeshore Dr. to SH 205 (S Goliad St.), Rockwall, TX, 75087
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025020873
$547K
Project Value
29,745
Square Feet
$18/sqft
Cost/SqFt
1y 6mo
Duration
Registered:Jun 9, 2025
Start:Sep 8, 2025
Target:Mar 12, 2027
Remaining:457 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Furnishing all labor, material, equipment, performing all work required for reconstruction of roadway concrete pavement, sidewalk, storm drain, water line, sanitary sewer, & replacement of parkway landscaping improvements.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
June 9, 2025
Review Complete
June 9, 2025
Construction Start
September 8, 2025
Expected Completion
March 12, 2027

๐Ÿ—บ๏ธProject Location

Loading map...

Quick Actions

TDLR ID: TABS2025020873

Property Owner

Design Firm

Registered Accessibility Specialist

๐Ÿ“‹
KIMBERLY J,GOSS
RAS #51
12720 HILLCREST ROAD STE 1040, DALLAS, TX 75230