📝Review Complete🏗️ New Construction💵 This project is privately funded, on private land for private use.
First Baptist Belton New Worship Center
1010 N Loop 121, Belton, TX, 76513
Construction50%
📊Project Metrics
TDLR #TABS2025021284$17.0M
Project Value
66,687
Square Feet
$255/sqft
Cost/SqFt
1y 2mo
Duration
Registered:Jun 13, 2025
Start:Aug 1, 2025
Target:Oct 1, 2026
Remaining:295 days
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
New 2 story 66,687 sq. ft. church worship building w/587 new parking stalls. Building will have a new connection to water and power, with a private sewer system.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
June 13, 2025
Review Complete
June 13, 2025
Construction Start
August 1, 2025
Expected Completion
October 1, 2026