๐Project Registered๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
BAWA East Surface Water Treatment Plant Phase II Expansion
5359 Grand Parkway, Baytown, TX, 77523
Pre-Construction15%
๐Project Metrics
TDLR #TABS2025021330$3.5M
Project Value
2,523
Square Feet
$1.39K/sqft
Cost/SqFt
2 years
Duration
Registered:Jun 16, 2025
Start:Apr 1, 2025
Target:Apr 1, 2027
Remaining:465 days
๐
Project Registered
Project has been registered with TDLR and is in pre-construction phase
๐Scope of Work
Construction of New Maintenance Shop (2438sf) and Additional Restroom to existing operations building (85sf).
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
June 16, 2025
Construction Start
April 1, 2025
Expected Completion
April 1, 2027
๐Related Projects
๐๏ธSame Design Firm
$7.3M totalProperty Owner
๐ค
Baytown Area Water Authority
Contact: Rafael Errisuriz
2123 Market Street, Baytown, Texas 77520
Design Firm
๐๏ธ
Carollo Engineers, Inc.
3 projects ยท $7.3M