North Boorman Lane
North Boorman Lane, Princeton, TX, 75407
Construction50%
๐Project Metrics
TDLR #TABS2025021786$4.6M
Project Value
12,371
Square Feet
$371/sqft
Cost/SqFt
7 months
Duration
Registered:Jun 23, 2025
Start:Jun 30, 2025
Target:Jan 30, 2026
Remaining:51 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Approximately 12,371 S.Y. of concrete pavement for Boorman Lane and approximately 3,848 S.Y. of concrete pavement for parking lot.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
June 23, 2025
Review Complete
June 23, 2025
Construction Start
June 30, 2025
Expected Completion
January 30, 2026
Property Owner
๐ค
City of Princeton
Contact: Tommy Mapp
2000 East Princeton Drive, Princeton, Texas 75407
Design Firm
๐๏ธ
Kimley-Horn
6 projects ยท $59.4M
260 East Davis Street, Suit 100, McKinney, Texas 75069