Howard Lane / Center Line Pass / The Lakes Blvd Intersection Improvements

Howard Lane and Center Line Pass/The Lakes Blvd., Austin, TX, 78753

๐Ÿ“ŠProject Overview

$1.6M
Est. Cost
17,613
Square Feet
8 months
Duration
652
Days Left

๐Ÿ“‹Scope of Work

Safety improvements including new sidewalk and curb ramps, pedestrian signal infrastructure, modifications to the right turn slip lane at Center Line Pass including installation of new signal, and median improvements. (17,613 SF)

๐Ÿ“…Project Timeline

Registered
June 24, 2025
Review Complete
June 24, 2025
Construction Start
January 15, 2027
Expected Completion
September 14, 2027

๐Ÿ—บ๏ธLocation

๐Ÿ“„Related Austin Permits

City permits found at this location

13802 1/2 THE LAKES BLVD
Same location

Install elec for landscape lighting & ariation pump eud

FinalElectrical PermitRepairMar 2007
Details
2007-107829 EP
๐Ÿ”งHeier Electric

Property Owner

๐Ÿ‘ค
City of Austin
Contact: Maggie Chan
6 total projects
5202 E Ben White Blvd Ste 550, Austin, Texas 78741
512-978-1705

Design Firm

๐Ÿ›๏ธ
Huitt-Zollars
6 total projects
9600 N Mopac Expy Ste 420, Austin, Texas 78759
512-689-2341

Registered Specialist

๐Ÿ“‹
JESUS E,LARDIZABAL
RAS #1051
3616 FAR WEST BLVD # 117288, AUSTIN, TX 78731
(512) 410-7059

Official Record

View on TDLR
ID: TABS2025021895