๐Review Complete๐ง Alteration/Renovation๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Bunton Creek Road
Bunton Creek Rd from Lehman Road to Twin Estatesdr, Kyle, TX, 78640
๐Project Overview
$34.3M
Est. Cost
1
Square Feet
1y 8mo
Duration
592
Days Left
๐Scope of Work
Bunton Creek Road improvements in Kyle, Texas spanning approximately 1.2 miles.
๐ Project Timeline
Registered
June 24, 2025
Review Complete
June 24, 2025
Construction Start
November 20, 2025
Expected Completion
July 15, 2027
๐บ๏ธLocation
๐Related Projects
Property Owner
๐ค
City of Kyle
Contact: Mike Trimble
6 total projects
100 W. Center Street, Kyle, Texas 78640
512-262-3024
Design Firm
Registered Specialist
๐
JESUS E,LARDIZABAL
RAS #1051
3616 FAR WEST BLVD # 117288, AUSTIN, TX 78731