โ
Inspection Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Garlic Creek Trail
1195 Heep Run, Buda, TX, 78610
๐Project Overview
$1.8M
Est. Cost
77,620
Square Feet
7 months
Duration
Complete
Status
๐Scope of Work
Installation of approximately 10,300 linear feet of 10' wide stabilized decomposed granite trail and 160 linear foot pedestrian bridge.
๐ Project Timeline
Registered
June 28, 2025
Inspection Complete
June 28, 2025
Construction Start
December 2, 2024
Expected Completion
July 7, 2025
๐บ๏ธLocation
๐Related Projects
Property Owner
๐ค
City of Buda
Contact: Blair Murski
4 total projects
405 E. Loop Street, Bldg.100, Buda, Texas 78610
(512) 523-0088
Design Firm
Registered Specialist
๐
JESUS E,LARDIZABAL
RAS #1051
3616 FAR WEST BLVD # 117288, AUSTIN, TX 78731
(512) 410-7059