๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Cedar Pond - Reserve T
8102 Red Cedar Circle, Humble, TX, 77396
Construction50%
๐Project Metrics
TDLR #TABS2025022326$160K
Project Value
9,800
Square Feet
$16/sqft
Cost/SqFt
3 months
Duration
Registered:Jun 30, 2025
Start:Aug 1, 2025
Target:Nov 1, 2025
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Construction of new 9,800 SF metal building with +/= 1,800 SF office space and +/- 8,000 SF shop area.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
June 30, 2025
Review Complete
June 30, 2025
Construction Start
August 1, 2025
Expected Completion
November 1, 2025
๐Related Projects
๐คBy Owner
$310K total๐๏ธBy Design Firm
$310K totalProperty Owner
๐ค
Cedar Pond Center LLC
Contact: David Terry
2 projects ยท $310K
PO Box 2016, Humble, Texas 77347
Design Firm
๐๏ธ
Deavers Engineering, LLC
2 projects ยท $310K
2839 N. Main Street, Stafford, Texas 77077