📝Review Complete🏗️ New Construction💵 This project involves public funds, public land, or is a Federally funded roadway project.
Kingsville Fire Station #3
2602 S 6th Street, Kingsville, TX, 78363
Construction50%
📊Project Metrics
TDLR #TABS2025023072$8.3M
Project Value
14,357
Square Feet
$575/sqft
Cost/SqFt
1 year
Duration
Registered:Jul 9, 2025
Start:Aug 4, 2025
Target:Aug 10, 2026
Remaining:243 days
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
This fire station consists of two apparatus bays, sleeping rooms for eight personnel, offices for four staff members, a conference room, a back-up EOC, a dayroom, a kitchen, and a dining room.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
July 9, 2025
Review Complete
July 9, 2025
Construction Start
August 4, 2025
Expected Completion
August 10, 2026