📋Project Registered🏗️ New Construction💵 This project involves public funds, public land, or is a Federally funded roadway project.
City of Premont, Cora Park Trail
199 S. Cora Street, Premont, TX, 78375
Pre-Construction15%
📊Project Metrics
TDLR #TABS2025023438$300K
Project Value
60,532
Square Feet
$5/sqft
Cost/SqFt
3 months
Duration
Registered:Jul 14, 2025
Start:Aug 4, 2025
Target:Nov 14, 2025
📋
Project Registered
Project has been registered with TDLR and is in pre-construction phase
📋Scope of Work
Design of new walking/ running trail in existing city park.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
July 14, 2025
Construction Start
August 4, 2025
Expected Completion
November 14, 2025