Aspermont ISD Athletic Locker Room & Classroom Reno
528 E. 7th Street, Aspermont, TX, 79402
Construction50%
๐Project Metrics
TDLR #TABS2025024061$2.5M
Project Value
5,000
Square Feet
$506/sqft
Cost/SqFt
8 months
Duration
Registered:Jul 22, 2025
Start:Oct 1, 2025
Target:May 15, 2026
Remaining:156 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Reno to existing boys' & girls' restrooms combining them into one encompassing nearly 5,000sf.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
July 22, 2025
Review Complete
July 22, 2025
Construction Start
October 1, 2025
Expected Completion
May 15, 2026
Property Owner
๐ค
Aspermont ISD
Contact: Superintendent Zach Morris
528 E. 7th Street, Aspermont, Texas 79402