๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

Blazing Trails Phase 2-Building 6 and Building 7

Deen Road at North Freeway, Fort Worth, TX, 76106
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025024591
$31.3M
Project Value
467,600
Square Feet
$67/sqft
Cost/SqFt
1y 1mo
Duration
Registered:Jul 29, 2025
Start:Aug 1, 2025
Target:Aug 31, 2026
Remaining:264 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

New construction of two shell building along with associated site improvements. (Building 6-188,160 sq. ft.)( Building 7-279,440 sq. ft.)

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 29, 2025
Review Complete
July 29, 2025
Construction Start
August 1, 2025
Expected Completion
August 31, 2026

๐Ÿ—บ๏ธProject Location

Loading map...

Quick Actions

TDLR ID: TABS2025024591

Design Firm

Registered Accessibility Specialist

๐Ÿ“‹
CONNIE,FLEMING
RAS #140
161 MEADOW POND CT, BRIDGEPORT, TX 76426