📝Review Complete🏗️ New Construction💵 This project involves public funds, public land, or is a Federally funded roadway project.
Lion’s Junction Family Waterpark
5000 S 5thStreet, Temple, TX, 76502
Construction50%
📊Project Metrics
TDLR #TABS2025025340$499K
Project Value
800
Square Feet
$624/sqft
Cost/SqFt
6 months
Duration
Registered:Aug 7, 2025
Start:Oct 1, 2025
Target:Apr 1, 2026
Remaining:112 days
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
Construction of a new building
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
August 7, 2025
Review Complete
August 7, 2025
Construction Start
October 1, 2025
Expected Completion
April 1, 2026
Property Owner
👤
City of Temple
Contact: Jordan Piel
6 projects · $7.2M
5 North Main St, Temple, Texas 76501
Design Firm
🏛️
Davis & Davis Inc recreational planning consultants
1805 West Park Row Dr,suite A, Arlington, Texas 7613