๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
SH 6 (CSJ: 0912-73-224)
Fr.: 2nd St To: 6th St & on Delaney Rd, Hitchcock, TX, 77563
Construction50%
๐Project Metrics
TDLR #TABS2025025692$3.7M
Project Value
29,790
Square Feet
$124/sqft
Cost/SqFt
5 months
Duration
Registered:Aug 12, 2025
Start:Mar 1, 2026
Target:Jul 16, 2026
Remaining:218 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Bicycle and pedestrian improvements consisting of sidewalks and shared-use path.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
August 12, 2025
Review Complete
August 12, 2025
Construction Start
March 1, 2026
Expected Completion
July 16, 2026
Property Owner
๐ค
TxDOT District: Houston
Contact: Mainul Khan, P.E.
6 projects ยท $107.4M
7600 Washington Avenue, Houston, Texas 77007
Design Firm
๐๏ธ
LJA Engineering, Inc.
6 projects ยท $78.4M
3600 East Sam Houston Parkway South, Suite 600, Houston, Texas 77042