๐Ÿ“Review Complete๐Ÿ”ง Additions to Existing Building๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Abilene Wylie ISD Additions & Renos for East Intermediate

4709 Oldham Lane, Abilene, TX, 79602
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025025736
$18.0M
Project Value
43,193
Square Feet
$417/sqft
Cost/SqFt
1y 4mo
Duration
Registered:Aug 13, 2025
Start:Nov 1, 2025
Target:Mar 1, 2027
Remaining:446 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Phase 2: 43,193sf addition including new classrooms & gym/storm shelter

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
August 13, 2025
Review Complete
August 13, 2025
Construction Start
November 1, 2025
Expected Completion
March 1, 2027

๐Ÿ—บ๏ธProject Location

Loading map...

Quick Actions

TDLR ID: TABS2025025736

Design Firm

Registered Accessibility Specialist

๐Ÿ“‹
LANDY,PERKINS
RAS #371
231 SUGARTREE CIR, LIPAN, TX 76462