๐Review Complete๐ง Alteration/Renovation๐ต This project is privately funded, on private land for private use.
Dell Round Rock 5 Comms Lab
200 Dell Way, Round Rock, TX, 78664
๐Project Overview
$1.0M
Est. Cost
2,500
Square Feet
3 months
Duration
15
Days Left
๐Scope of Work
MODIFICATION TO THE LAYOUT OF EXISTING EQUIPMENT AND ASSOCIATED STORAGE AREAS, INSTALLATION OF NEW MECHANICAL AND ELECTRICAL EQUIPMENT AND INFRASTRUCTURE, AND INSTALLATION OF NEW OWNER PROVIDED SERVER EQUIPMENT.
๐ Project Timeline
Registered
August 14, 2025
Review Complete
August 14, 2025
Construction Start
September 15, 2025
Expected Completion
December 15, 2025
๐บ๏ธLocation
๐Related Projects
Property Owner
๐ค
Dell Technologies
Contact: Jared Frazier
6 total projects
1 Dell Way, Round Rock, Texas 78682
(512) 638-3506
Design Firm
Registered Specialist
๐
MARK S,ROBINSON
RAS #1561
18704 JANA PATRICE DR, PFLUGERVILLE, TX 78660
(512) 459-2121