๐Review Complete๐ง Renovation/Alteration๐ต This project is privately funded, on private land for private use.
Permian Resources - Level 3 Phase 3 Renovations
300 N Marienfeld St., Suite 1000, Midland, TX, 79701
Construction50%
๐Project Metrics
TDLR #TABS2025026021$1.3M
Project Value
5,775
Square Feet
$225/sqft
Cost/SqFt
3 months
Duration
Registered:Aug 15, 2025
Start:Sep 1, 2025
Target:Dec 12, 2025
Remaining:2 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Final renovation finish out of the third floor. This includes a new breakroom and renovated restrooms.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
August 15, 2025
Review Complete
August 15, 2025
Construction Start
September 1, 2025
Expected Completion
December 12, 2025
๐Related Projects
๐๏ธBy Design Firm
$3.2M totalProperty Owner
๐ค
Permian Resources Corporation LLC
Contact: Jonny Heins
300 N Marienfeld St. Suite 1000, Midland, Texas 79701