๐Project Registered๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Cargill Friona
1530 US Highway 60, Friona, TX, 79035
Pre-Construction15%
๐Project Metrics
TDLR #TABS2025026064$9.5M
Project Value
2,044
Square Feet
$4648/sqft
Cost/SqFt
1y 1mo
Duration
Registered:Aug 18, 2025
Start:Apr 1, 2025
Target:Apr 30, 2026
Remaining:141 days
๐
Project Registered
Project has been registered with TDLR and is in pre-construction phase
๐Scope of Work
Construction of a new 2,044 sf security building and new 4,654 sf maintenance building.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
August 18, 2025
Construction Start
April 1, 2025
Expected Completion
April 30, 2026