๐Review Complete๐ง Renovation/Alteration๐ต This project is privately funded, on private land for private use.
Edward Jones Branch Office
851 E. Travis St., La Grange, TX, 78945
Construction50%
๐Project Metrics
TDLR #TABS2025026442$107K
Project Value
1,880
Square Feet
$57/sqft
Cost/SqFt
3 months
Duration
Registered:Aug 21, 2025
Start:Oct 1, 2025
Target:Dec 16, 2025
Remaining:6 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Complete renovation to building interior
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
August 21, 2025
Review Complete
August 21, 2025
Construction Start
October 1, 2025
Expected Completion
December 16, 2025