✅Inspection Complete🏗️ New Construction💵 This project involves public funds, public land, or is a Federally funded roadway project.
Modular Buildings Lago Vista Intermediate School
20801 FM 1431, Lago Vista, TX, 78645
📊Project Overview
$1.4M
Est. Cost
9,728
Square Feet
4 months
Duration
Complete
Status
📋Scope of Work
Installation of two modular classroom buildings 28x64 and 64x124
📅Project Timeline
Registered
August 29, 2025
Inspection Complete
August 29, 2025
Construction Start
May 5, 2025
Expected Completion
August 27, 2025