๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Greenville Marriott SHS TPS
2005 CENTERPORT LN. GREENVILLE, TX 75402, Greenville, TX, 75402
Construction50%
๐Project Metrics
TDLR #TABS2026000338$8.0M
Project Value
65,970
Square Feet
$121/sqft
Cost/SqFt
7 months
Duration
Registered:Sep 5, 2025
Start:Oct 1, 2025
Target:Apr 30, 2026
Remaining:141 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Conversion of 4 Story Hotel to a Sprinhill Suites and a Amenity Center Addition
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
September 5, 2025
Review Complete
September 5, 2025
Construction Start
October 1, 2025
Expected Completion
April 30, 2026