๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
E-Space (Manufacturing Facility) - Building V3 & V4
5000 S Collins St, Arlington, TX, 76018
Construction50%
๐Project Metrics
TDLR #TABS2026001142$107.0M
Project Value
480,000
Square Feet
$223/sqft
Cost/SqFt
1y 5mo
Duration
Registered:Sep 17, 2025
Start:Feb 1, 2026
Target:Jun 27, 2027
Remaining:564 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
New manufacturing facility to be constructed on the Arlington Municipal Airport site, on land near the existing control tower. The building will be approximately 480,000 sf, consisting of manufacturing and office space.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
September 17, 2025
Review Complete
September 17, 2025
Construction Start
February 1, 2026
Expected Completion
June 27, 2027
Property Owner
๐ค
City of Arlington
Contact: Lyndsay Mitchell
6 projects ยท $121.3M
PO Box 90231, Arlington, Texas 76004
Design Firm
Registered Accessibility Specialist
Tenant
๐ข
Gwen Sisto, E-Space