๐Review Complete๐ง Additions to Existing Building๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Willowridge High School Fine Arts Addition and Renovation
16301 Chimney Rock Rd, Houston, TX, 77053
Construction50%
๐Project Metrics
TDLR #TABS2026001172$14.3M
Project Value
103,300
Square Feet
$138/sqft
Cost/SqFt
1y 9mo
Duration
Registered:Sep 17, 2025
Start:Mar 1, 2026
Target:Dec 1, 2027
Remaining:721 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
The new 10,300 SF Fine Arts Addition will house a new black box theater, classrooms (drama, orchestra, choir), and 2 small practice rooms. The renovation scope includes some updates to the existing auditorium, band hall, and art classrooms.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
September 17, 2025
Review Complete
September 17, 2025
Construction Start
March 1, 2026
Expected Completion
December 1, 2027
Property Owner
๐ค
Fort Bend ISD
Contact: Nancy Lane
6 projects ยท $14.6M
2323 Texas Parkway, Missouri City, Texas 77489