📋Project Registered🔧 Renovation/Alteration💵 This project is privately funded, on private land for private use.
FIRST BAPTIST CHURCH OF COPPERAS COVE
300 W. Ave. B, Copperas Cove, TX, 76522
Pre-Construction15%
📊Project Metrics
TDLR #TABS2026001313$726K
Project Value
10,914
Square Feet
$67/sqft
Cost/SqFt
4 months
Duration
Registered:Sep 19, 2025
Start:Oct 6, 2025
Target:Jan 30, 2026
Remaining:51 days
📋
Project Registered
Project has been registered with TDLR and is in pre-construction phase
📋Scope of Work
Scope of work: restoration of First Baptist Church of Copperas Cove Worship Center. Includes demolition, roof/truss repair, framing, windows/doors, drywall, paint, flooring, carpentry, cabinetry, and MEP systems if needed. All per codes/permits.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
September 19, 2025
Construction Start
October 6, 2025
Expected Completion
January 30, 2026
Property Owner
👤
FIRST BAPTIST CHURCH OF COPPERAS COVE
Contact: Mark Kemp
300 W AVENUE B, COPPERAS COVE, Texas 76522