๐Review Complete๐ง Renovation/Alteration๐ต This project is privately funded, on private land for private use.
CAPTAIN CRAB
20185 US-59, NEW CANEY, TX 77357, New Caney, TX, 77357
Construction50%
๐Project Metrics
TDLR #TABS2026002544$400K
Project Value
5,600
Square Feet
$71/sqft
Cost/SqFt
4 months
Duration
Registered:Oct 3, 2025
Start:Dec 10, 2025
Target:Apr 20, 2026
Remaining:131 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
INTERIOR ALTERATION TO AN EXISTING SPACE
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
October 3, 2025
Review Complete
October 3, 2025
Construction Start
December 10, 2025
Expected Completion
April 20, 2026
๐Related Projects
๐คBy Owner
$860K totalProperty Owner
๐ค
Andrew Nguyen
Contact: Jeff Lam
3 projects ยท $860K
2855 Mangum Rd., Suite A588, Houston, Texas 77092