๐Review Complete๐ง Renovation/Alteration๐ต This project is privately funded, on private land for private use.
Target Fort Worth TX T0758
8550 Tom Landry Freeway, Fort Worth, TX, 76120
Construction50%
๐Project Metrics
TDLR #TABS2026002725$2.1M
Project Value
40,000
Square Feet
$53/sqft
Cost/SqFt
4 months
Duration
Registered:Oct 7, 2025
Start:Apr 27, 2026
Target:Aug 31, 2026
Remaining:264 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Renovation of interior and exterior of existing Target store
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
October 7, 2025
Review Complete
October 7, 2025
Construction Start
April 27, 2026
Expected Completion
August 31, 2026
Property Owner
๐ค
Target
Contact: Angela Feyder
6 projects ยท $13.2M
1000 Nicollet Mall, Minneapolis, Minnesota 55403