๐Review Complete๐ง Renovation/Alteration๐ต This project is privately funded, on private land for private use.
MCD DFW GATE A15 - DFW, TX
DFW INTERNATIONAL AIRPORT TERMINAL A, Dfw Airport, TX, 75261
Construction50%
๐Project Metrics
TDLR #TABS2026002947$750K
Project Value
2,784
Square Feet
$269/sqft
Cost/SqFt
4 months
Duration
Registered:Oct 9, 2025
Start:Dec 1, 2025
Target:Mar 31, 2026
Remaining:111 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Tenant Finishout for McDonalds in DFW Airport Termina A
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
October 9, 2025
Review Complete
October 9, 2025
Construction Start
December 1, 2025
Expected Completion
March 31, 2026
Property Owner
๐ค
MCDONALD'S USA, LLC
Contact: PATRICK PIEHL
6 projects ยท $8.3M
110 N. CARPENTER STREET, CHICAGO, Illinois 60607
Design Firm
๐๏ธ
JAW ARCHITECTS, INC.
6 projects ยท $12.4M
6115 CAMP BOWIE BLVD STE 200, FORT WORTH, Texas 76116