📝Review Complete🏗️ New Construction💵 This project is privately funded, on private land for private use.
Trinity Crossing Convenience Store
3901 Post Oak Blvd, Fort Worth, TX, 76040
Construction50%
📊Project Metrics
TDLR #TABS2026003204$3.0M
Project Value
4,140
Square Feet
$725/sqft
Cost/SqFt
8 months
Duration
Registered:Oct 13, 2025
Start:Mar 16, 2026
Target:Nov 16, 2026
Remaining:341 days
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
New 4140 sf convenience store
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
October 13, 2025
Review Complete
October 13, 2025
Construction Start
March 16, 2026
Expected Completion
November 16, 2026
Property Owner
👤
Himalayan Properties LLC
Contact: Jack Roseberry
431 Southridge Way, Irving, Texas 75063