๐Project Registered๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Main Entry Improvements at Allen City Hall
305 Century Parkway, Allen, TX, 75013
Pre-Construction15%
๐Project Metrics
TDLR #TABS2026003527$500K
Project Value
5,300
Square Feet
$94/sqft
Cost/SqFt
5 months
Duration
Registered:Oct 16, 2025
Start:Dec 1, 2025
Target:Apr 24, 2026
Remaining:135 days
๐
Project Registered
Project has been registered with TDLR and is in pre-construction phase
๐Scope of Work
New sidewalks, steps, ramps, hand railings, retaining walls, landscape and irrigation
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
October 16, 2025
Construction Start
December 1, 2025
Expected Completion
April 24, 2026