📝Review Complete🏗️ New Construction💵 This project is privately funded, on private land for private use.
Dealers Electric
4013 Bell Dr, Temple, TX, 76502
Construction50%
📊Project Metrics
TDLR #TABS2026003729$150K
Project Value
12,058
Square Feet
$12/sqft
Cost/SqFt
2 months
Duration
Registered:Oct 20, 2025
Start:Nov 1, 2025
Target:Dec 23, 2025
Remaining:13 days
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
Construction of a new, one-story building with office space and warehouse.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
October 20, 2025
Review Complete
October 20, 2025
Construction Start
November 1, 2025
Expected Completion
December 23, 2025