📝Review Complete🏗️ New Construction💵 This project is privately funded, on private land for private use.
Camp for All
3802 Caney Creek Road, Chappell Hill, TX, 77426
Construction50%
📊Project Metrics
TDLR #TABS2026003929$748K
Project Value
7,500
Square Feet
$100/sqft
Cost/SqFt
1 year
Duration
Registered:Oct 21, 2025
Start:Nov 3, 2025
Target:Nov 3, 2026
Remaining:328 days
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
New Equestrian Barn
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
October 21, 2025
Review Complete
October 21, 2025
Construction Start
November 3, 2025
Expected Completion
November 3, 2026