๐Ÿ“ŠProject Overview

$1.1M
Est. Cost
1,100
Square Feet
3 months
Duration
243
Days Left

๐Ÿ“‹Scope of Work

Renovation of existing and addition of one new dorm room on the first floor of Tower Hall.

๐Ÿ“…Project Timeline

Registered
October 28, 2025
Review Complete
October 28, 2025
Construction Start
May 11, 2026
Expected Completion
July 31, 2026