📝Review Complete🔧 Renovation/Alteration💵 This project is privately funded, on private land for private use.
Project Eagle - Final Connections
15200 Heritage Pkwy, Fort Worth, TX, 76177
Construction50%
📊Project Metrics
TDLR #TABS2026004440$6.0M
Project Value
200,000
Square Feet
$30/sqft
Cost/SqFt
3 months
Duration
Registered:Oct 28, 2025
Start:Dec 1, 2025
Target:Feb 28, 2026
Remaining:80 days
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
The scope of this project is to connect the chilled water, compressed air, vacuum, exhaust, and power to the final location and connection of the owner's process equipment.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
October 28, 2025
Review Complete
October 28, 2025
Construction Start
December 1, 2025
Expected Completion
February 28, 2026
Property Owner
👤
WISTRON INFOCOMM (USA) CORP
Contact: Froggy Lin
700 N Zaragoza Rd Ste N, El Paso, Texas 79907