📝Review Complete🔧 Renovation/Alteration💵 This project is privately funded, on private land for private use.
Technimark Finishout
900 W Zaragosa Dr, Pharr, TX, 78577
Construction50%
📊Project Metrics
TDLR #TABS2026004562$575K
Project Value
1,800
Square Feet
$319/sqft
Cost/SqFt
4 months
Duration
Registered:Oct 29, 2025
Start:Nov 15, 2025
Target:Mar 15, 2026
Remaining:95 days
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
Addition of a finishout 17,956 SF
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
October 29, 2025
Review Complete
October 29, 2025
Construction Start
November 15, 2025
Expected Completion
March 15, 2026
Property Owner
👤
PHARR BRIDGE INVESTMENT COMPANY LP
Contact: Isaac Ochoa
3501 W. Utility Dr, Pharr, Texas 78577