๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Traffic Signal Installation for Plano Parkway at Warmington Drive

Plano Parkway & Warmington Drive, Carrollton, TX, 75010
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2026006075
$400K
Project Value
10,000
Square Feet
$40/sqft
Cost/SqFt
5 months
Duration
Registered:Nov 17, 2025
Start:Feb 2, 2026
Target:Jun 30, 2026
Remaining:202 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Installing a new traffic signal.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
November 17, 2025
Review Complete
November 17, 2025
Construction Start
February 2, 2026
Expected Completion
June 30, 2026

๐Ÿ—บ๏ธProject Location

Loading map...

Quick Actions

TDLR ID: TABS2026006075

Property Owner

Design Firm

๐Ÿ›๏ธ
Mcadams
4400 State Highway 121 Suite 800, Lewisville, Texas 75056

Registered Accessibility Specialist

๐Ÿ“‹
CASEY JOE,ANDERSON
RAS #1587