Agua Dulce Independent School District - Welding Lab Expansion
1603 Hearn Ave, Agua Dulce, TX 78330, Agua Dulce, TX, 78330
Pre-Construction15%
📊Project Metrics
TDLR #TABS2026008038$2.0M
Project Value
2,400
Square Feet
$833/sqft
Cost/SqFt
1y 10mo
Duration
Registered:Dec 15, 2025
Start:Feb 3, 2025
Target:Dec 7, 2026
Remaining:352 days
📋
Project Registered
Project has been registered with TDLR and is in pre-construction phase
📋Scope of Work
Expanding a metal welding building with a new shop, classroom, restrooms, office, and storage.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
December 15, 2025
Construction Start
February 3, 2025
Expected Completion
December 7, 2026