๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

SHENANDALE - CLIFTON RIDGE TO FLINT HILL

SHENANDALE ST., San Antonio, TX 78230, San Antonio, TX, 78230
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB7803099
$84K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
1 months
Duration
Registered:Oct 21, 2016
Start:Sep 1, 2016
Target:Oct 1, 2016
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Sidewalk, curb and driveway construction

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
October 21, 2016
Construction Start
September 1, 2016
Expected Completion
October 1, 2016