๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

City of Schertz Main Street Sidewalk Addition Project

Main Street from Schertz PKWY to Randolph Ave., Schertz, TX 78154, Schertz, TX, 78154
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020021622
$200K
Project Value
7,700
Square Feet
$26/sqft
Cost/SqFt
3 months
Duration
Registered:Aug 3, 2020
Start:Aug 17, 2020
Target:Nov 17, 2020
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Install new sidewalk along south side of Main Street from Schertz Parkway to Randolph Avenue. Replace all curb and gutter. Replace driveway approaches to be compliant.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
August 3, 2020
Construction Start
August 17, 2020
Expected Completion
November 17, 2020

Quick Actions

TDLR ID: TABS2020021622

Property Owner

๐Ÿ‘ค
City of Schertz
4 projects ยท $9.7M
1400 Schertz Parkway, Schertz, Texas 78154

Design Firm

Registered Accessibility Specialist

๐Ÿ“‹
CATHERINE P,GARCIA
RAS #1205
221 W RHAPSODY DR # 102, SAN ANTONIO, TX 78216